Weekly Project Status Report

Project name  

BPA- Apply

Week Ending  15/11/2019
Prepared ByPhani & Elzan
Date Prepared19/11/2019

...

Accomplishments Of The Week


  1. We continued to explore stories and PRD, posted questions in the stories
  2. We continued to explore the front-end framework and able to develop Application forms 
  3. We are working on mock JSON integration
  4. We have worked on the stories breakdown with the rough estimates for Phase 1
  5. We have continued to explore the Back end services by setting the kafka and codebase in our local machines
  6. eGov users and TL services code flow explored
  7. Explored workflow engine and configurations
  8. Worked on the API contract required in applications for new construction.




Plans For Next Week

  1. Platform team to share the API contract for WT by this week20th Nov.
  2. Sankar to answer all the functional queries raised by WT team and platform team.
  3. WT team to share a story break down for phase1 with the estimates.
  4. Actual back end development would start this week.
  5. Static screen for apply for new construction end to end to be ready by end of week
  6. Siva to do static screen review with Sankar and Elzan for application.

...