Activity | Stakeholders from In-house | Supporting Documents |
---|---|---|
Production Environment Setup and Configuration |
| |
UAT Environment Setup and Configuration | ||
Source Code Repository | ||
QA & UAT Instances | ||
Production Servers | ||
CI & CD Pipelines | ||
Github | ||
Jenkins | ||
Nexus | ||
Database Setup | ||
Code Handover | ||
Q & A |
Transition - Low level Plan
Low level transition plan details out the week wise plan for the transition process. The transition process will be spread across 10 weeks with last 2 weeks reserved for hand holding.
Group 1 | Group 2 | Group 3 | Group 4 |
---|---|---|---|
|
|
|
|
Week-wise Plan [Applies to all Groups except Group 4]
Week # | Activity |
---|---|
Week 1 | Application Introduction |
Weeks 2 to 5 | Application Deepdive |
Week 6 | Reverse KT |
Weeks 7 & 8 | Q & A |
Weeks 9 & 10 | Handhold support |
eGov Team for the transition
Transition process will be assisted by following team from eGov:
Sl. No. | Role | Resources |
---|---|---|
01. | Technical Manager | 01 |
02. | Project Manager | 01 |
03. | Technical Lead | 03 |
04. | Junior Business Analyst | 03 |
05. | Senior Software Engineer | 03 |
06. | QA Engineer | 02 |
07. | DevOps Engineer | 01 |