Activity

Stakeholders from In-house

Supporting Documents

Production Environment Setup and Configuration

  1. Project Manager

  2. Architect

  3. DevOps Engineer

UAT Environment Setup and Configuration

Source Code Repository

QA & UAT Instances

Production Servers

CI & CD Pipelines

Github

Jenkins

Nexus

Database Setup

Code Handover

Q & A

Transition - Low level Plan

Low level transition plan details out the week wise plan for the transition process. The transition process will be spread across 10 weeks with last 2 weeks reserved for hand holding.

Group 1

Group 2

Group 3

Group 4

  1. Property Tax & Vacant Land Tax

  2. Water Charges

  3. Sewerage Charges

  4. Financial Management

  5. Non-tax Revenue

  6. Ward Secretariat Integration

  7. meeSeva Integration

  1. Asset Management

  2. Lease & Agreements

  3. Advertisement Tax

  4. Business Analytics & Dashboards

  5. Inter-Department Integration

  6. GIS Integration

  7. CDMA/ULB Portals

  8. Citizen Portal

  1. Infrastructure + Common Services

  2. Human Resource Management

  3. Public Grievance Redressal

  4. Council Management

  5. Legal Case Management

  6. D & O Trade License

  7. Marriage Registration

  1. DevOps

Week-wise Plan [Applies to all Groups except Group 4]

Week #

Activity

Week 1

Application Introduction

Weeks 2 to 5

Application Deepdive

Week 6

Reverse KT

Weeks 7 & 8

Q & A

Weeks 9 & 10

Handhold support

eGov Team for the transition

Transition process will be assisted by following team from eGov:

Sl. No.

Role

Resources

01.

Technical Manager

01

02.

Project Manager

01

03.

Technical Lead

03

04.

Junior Business Analyst

03

05.

Senior Software Engineer

03

06.

QA Engineer

02

07.

DevOps Engineer

01