Sl No

Checklist

Yes/No/Partially

Reference link

Owner

Remarks

1

Development is completed for all the features that are part of the release.

Yes

High-level features for 2.7 Release

Sirish (Unlicensed)

Development completed as a part of this release along with B&D module.

2

Test cases are documented by the QA team, reviewed by the product owners and test results are updated in the test cases sheet.

Yes

Test Cases DIGIT 2.7 Release

Bhavani Sruti

3

The incremental demo of the features showcased during the sprint showcase and feedback incorporated. If possible list out the JIRA tickets for feedback.

NoYes

Abhishek Suresh

Sirish (Unlicensed)

National Dashboard sprint showcase completed on 25th Feb 2022.
Birth and Death Sprint/Release showcase planned for 27th May 2022.

4

UI/UX Audit review by UX Architect is completed along with feedback incorporation for any changes in UI/UX.

No

UI/UX Audit feedback

B&D Feedback

JaganKumar

Sirish (Unlicensed)

UX Architect feedback in the form of bugs and improvements done.

5

Incremental demos to the product owners are completed as part of the sprint and feedbacks are incorporated.

Yes

Sirish (Unlicensed)

Multiple Incremental demos were completed during the sprint cycle.

6

QA signoff is completed by the QA team and communicated to the product owners. All the tickets QA signoff status is updated in the JIRA.

Yes

Bhavani Sruti

QA signoff was completed.
Incremental sign-off dates

  1. Notification for different channels - W&S, PT, and TL

  2. UI/UX for revamp update Mobile number

  3. Employee City Change

  4. Employee Profile

  5. Citizen Profile

7

UI, API Technical documents are updated for the release along with the configuration documents. 

Yes

Tech Docs

Sirish (Unlicensed)

These docs will be Published to Gitbook within 2 working days of the release.

8

UAT promotion and regression testing from the QA team is completed. QA team has shared the UAT regression test cases with the product owners.

Yes

UAT Regression Test Cases

Bhavani Sruti

9

API Automation scripts are updated for new APIs or changes to any existing APIs for the release. API automation regression is completed on UAT, the automation test results are analyzed and necessary actions are taken to fix the failure cases. Publish the list of failure use cases with a reason for failure and the resolution taken to fix these failures for the release.

Yes

DIGIT 2.7 API scripts

Digit 2.7 API Automation reports

Bhavani Sruti

10

The API backward compatibility testing is completed.

Yes

Backward Compatibility Testing Report

Bhavani Sruti

11

The communication is shared with the product owners for the completion of UAT promotion and regression by the QA team. The product owners have to give a Product signoff within one week of this communication.

Yes

Bhavani Sruti

Sirish (Unlicensed)

OBPS is not getting delivered for this release. Planned dates will be communicated by 25th May

12

UAT Product Signoff communication is received from the Product owners along with the release notes and User guides (if applicable).

Yes

Sirish (Unlicensed)

Product Owners

Product sign-off received for the below :

  • National DSS

  • State DSS

    • National Dashboard Ingest API

    • National Dashboard for PT, TL, OBPS, PGR, W&S, mCollect, and Fire NOC

    • State level DSS of OBPS, W&S, Fire NOC and mCollect.

    • NUGP STQC Security fixes

    • PT UI/UX Audit

    Testing
    • Feedbacks

    • TL UI/UX

    audit testing
    • Audit Feedbacks

    • PGR UI/UX Enhancements

    audit
    • Audit Feedbacks

    • PT

    -Common Search and lightweight create
    -Pt Integration with TL

    1. UI/UX for revamp update Mobile number

    2. Employee City Change

    3. Employee Profile

    10. Citizen Profile
    11.
    • common Search, PT lightweight create and integrate with TL.

    • Notification for different channels - W&S, PT, and TL


    12.
    • .

    • Common UI/UX - Citizen Profile, Employee Profile, and Multi Tenancy Selection

    • Birth and Death

    Module - Core service and
    • module, State DSS

    ,
    • and National Dashboard for Birth and Death.

    13

    The GIT tags and releases are created for the code changes for the release.

    NoYes

    GIT Tag details

    Sirish (Unlicensed)

    In-progress

    14

    Verify whether the Release notes are updated

    Yes

    Release Notes DIGIT 2.7

    Sirish (Unlicensed)

    15

    Verify whether all UAT Builds are updated along with the GIT tag details.

    Yes

    Service Build Updates 2.7

    Sirish (Unlicensed)

    16

    Verify whether all MDMS, Configs, InfraOps configs updated.

    Yes

    MDMS & Configuration Updates 2.7

    Sirish (Unlicensed)

    17

    Verify whether all docs will be Published to http://docs.digit.org by the Technical Writer as part of the release.

    No

    Sirish (Unlicensed)

    Anjoo

    It will be done within a week post the release communication.

    18

    Verify whether all test cases are up to date and updated along with necessary permissions to view the test cases sheet. The test cases sheet is verified by the Test Lead.

    Yes

    TestCases

    Bhavani Sruti

    19

    Verify whether the UAT credentials sheet is updated with the details of new Users and Roles if any

    Yes

    UAT Credentials

    Bhavani Sruti

    20

    Verify whether all the localization data was added in UAT including Hindi and updated in Release Kits.

    Yes

    Localization Localisation

    Lata Naik Bhavani Sruti

    21

    Verify whether the product release notes and user guides are updated and published

    Yes

    National Dashboard and State DSS Release Notes 2.7

    Common Features UI/UX Revamp 2.7

    Property Tax Release Notes 2.7

    Birth & Death Release Notes 2.7

    Sirish (Unlicensed)

    OBPS release is not part of the this release due to the following UAT issues . Bug fixing and internal testing is in-progress.

    22

    The Internal release communication along with all the release artefacts are shared by the Engineering team.

    No

    Sirish (Unlicensed) Yes

    Sathish P

    Shared the release communication on 20 May 2022.

    23

    The Demo of released features is done by the product team as part of the Sprint/Release showcase.

    Partially done

    Abhishek Suresh /Sirish

    National Dashboard Demo is completed on Feb 25th 2022.

    Another Sprint showcase scheduled on May 27th 2022.

    24

    The Release communication to partners is shared by the GTM team and the Webinar is arranged by the GTM team after the release communication - within 2-4 weeks of the release.

    No

    Sirish (Unlicensed)

    This will be done by GTM post to the Release communication from Engineering

    25

    Technical and Product workshops/demos are conducted by the Engineering and Product team based on the need from the implementation team and partners. 

    No

    Sirish (Unlicensed) Partially

    Sirish

    Product Owners

    The Technical KT is given to the NUDM team for the Beta release. Release KT and enablement will be done post to the release.

    26

    Plan for upgrading the staging/demo instance with the release product - within 2-4 weeks based on the period where no demos are planned from staging for the previous version of the released product.

    No