@Sl No

Checklist

Yes/No/Partially

Reference link

Owner

Reviewer

Remarks

1

Development is completed for all the features that are part of the release.

Yes

Kaviyarasan P

Sathish P

code is frozen by 10-Feb-2023

2

Test cases are documented by the QA team, reviewed by the product owners and test results are updated in the test cases sheet.

Yes

Test Cases for Digit 2.8 Release

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

P. Sankar

3

The incremental demo of the features showcased during the sprint showcase and feedback incorporated. If possible list out the JIRA tickets for feedback.

Yes

Kaviyarasan P

P. Sankar

Nirbhay Singh

Yes, incremental demos are shown during the development sprints.

4

UI/UX Audit review by UX Architect is completed along with feedback incorporation for any changes in UI/UX.

Yes

JaganKumar

Antriksh Kumar

Vamshikrishna Kole (Unlicensed)

P. Sankar

UI/UX audit is done and review comments are incorporated.

5

Incremental demos to the product owners are completed as part of the sprint and feedbacks are incorporated.

Yes

https://drive.google.com/drive/u/1/folders/1Pkj2J2P2epfM5IR046GXdfHHHR__0-YV

Kaviyarasan P

P. Sankar

6

QA signoff is completed by the QA team and communicated to the product owners. All the tickets QA signoff status is updated in the JIRA.

Yes

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

P. Sankar

QA signoff was completed.
Incremental sign-off dates

3rd Nov 2022

  • WnS

  • BillAmendment

  • BillGenie

13th Dec 2022

  • PT

  • TL

  • PGR

  • OBPS

  • B&D Tabular Reports - in old UI/UX

  • Mis Collection

  • National Dashboard FAQ & About screen

  • Product specific pages

  • Navigation redirection from New UI to old UI
    2nd Feb 2023

  • Surveys

7

UI, API Technical documents are updated for the release along with the configuration documents. 

Yes

Kaviyarasan P

Vamshikrishna Kole (Unlicensed)

Featured in the release page and master migration document

8

UAT promotion and regression testing from the QA team is completed. QA team has shared the UAT regression test cases with the product owners.

Yes

Navyashree

KeerthiBhaskara-eGov

P. Sankar

Test Cases for Digit 2.8 Release

9

API Automation scripts are updated for new APIs or changes to any existing APIs for the release. API automation regression is completed on UAT, the automation test results are analyzed and necessary actions are taken to fix the failure cases. Publish the list of failure use cases with a reason for failure and the resolution taken to fix these failures for the release.

No

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

Not picked Up in this release

10

The API backward compatibility testing is completed.

Yes

https://drive.google.com/drive/folders/1caJHTwm0fV-IALOmJO8WkNQfUcfAmZZJ?usp=share_link

Navyashree G (Unlicensed)

Kaviyarasan P

Use cases are ran with the existing scripts, no new API structure changes in the new release. new scripts for 2.8 will taken up in upcoming sprints

11

The communication is shared with the product owners for the completion of UAT promotion and regression by the QA team. The product owners have to give a Product signoff within one week of this communication.

Yes

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

P. Sankar

UAT signoff was completed on

  • W&S

  • Bill Amendment

  • BillGenie

  • PT

  • TL

  • PGR

  • OBPS

  • B&D Tabular Reports - in old UI/UX

  • Mis Collection

  • National Dashboard FAQ & About screen

  • Product specific pages

  • Navigation redirection from New UI to old UI

  • Surveys

  • National Dashboard Adaptor Integration Testing

  • NationalDashBoard 3 New KPI

  • Fire NOC

  • Finance DSS

12

UAT Product Signoff communication is received from the Product owners along with the release notes and User guides (if applicable).

Yes

https://app.gitbook.com/o/-MEQmzNGXk5ajuZujG7E/s/UYtUmELy66UydIQtJOn5/~/changes/61/platform/release-notes

Kaviyarasan P

Product Owners

P. Sankar

All prods are signed off , release notes and user guides are updates

  • W&S

  • Bill Amendment

  • BillGenie

  • PT

  • TL

  • PGR

  • OBPS

  • B&D Tabular Reports - in old UI/UX

  • Mis Collection

  • National Dashboard FAQ & About screen

  • Product specific pages

  • Navigation redirection from New UI to old UI

  • Surveys

  • Fire NOC

13

The GIT tags and releases are created for the code changes for the release.

yes

Service Build Updates 2.8

Kaviyarasan P

14

Verify whether the Release notes are updated

Yes

Kaviyarasan P

15

Verify whether all UAT Builds are updated along with the GIT tag details.

Yes

Service Build Updates 2.8

Kaviyarasan P

16

Verify whether all MDMS, Configs, InfraOps configs updated.

Yes

Kaviyarasan P

17

Verify whether all docs will be Published to http://urban.digit.org by the Technical Writer as part of the release.

Yes

Kaviyarasan P

Anjoo Narayan

18

Verify whether all test cases are up to date and updated along with necessary permissions to view the test cases sheet. The test cases sheet is verified by the Test Lead.

Yes

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

19

Verify whether the UAT credentials sheet is updated with the details of new Users and Roles if any

Yes

https://docs.google.com/spreadsheets/d/15p6dmlVUXvopvzyyG06ty2rxtffSMQxN5F2l2FSWoFA/edit?usp=sharing

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

20

Verify whether all the localisation data was added in UAT including Hindi and updated in Release Kits.

Yes

Localization

Navyashree G (Unlicensed)

KeerthiBhaskara-eGov

21

Verify whether the product release notes and user guides are updated and published

Yes

https://app.gitbook.com/o/-MEQmzNGXk5ajuZujG7E/s/UYtUmELy66UydIQtJOn5/~/changes/61/platform/release-notes

Product Owners

P. Sankar

Release notes and user guides are published in gitbooks.

22

The Demo of released features is done by the product team as part of the Sprint/Release showcase.

Yes

https://drive.google.com/drive/u/0/folders/1sO6jvGp9jickOGAWPInm2QbzohfbldFa

Nirbhay Singh

P. Sankar

Yes - all features of 2.8 are demoed to the eGov team.

23

Technical and Product workshops/demos are conducted by the Engineering and Product team to the implementation team (Implementation handover)

Yes

Kaviyarasan P

Pradeep Kumar

Migration process has been explained, all the Docs are added to the master migration doc based on feedback from impel team

24

Architect SignOff and Technical Quality Report

Yes

Kaviyarasan P

Sign off is given with privacy disabled and encryption process disabled for W&S,PT modules. Redesign of privacy will be taken up by DPG based on the shortcomings shared in Tech council.

25

Success Metrics and Product Roadmap

https://app.gitbook.com/o/-MEQmzNGXk5ajuZujG7E/s/UYtUmELy66UydIQtJOn5/~/changes/61/platform/release-notes

P. Sankar

Product road map post digit 2.8 is not clear yet as we have less visibility and trimming down the operations/resources in urban team.

26

Adoption Metrics

https://app.gitbook.com/o/-MEQmzNGXk5ajuZujG7E/s/UYtUmELy66UydIQtJOn5/~/changes/61/platform/release-notes

Ajay Rawat
P. Sankar

27

Program Roll-out Plan

Pradeep Kumar

28

Implementation checklist

Implementation Checklist

Pradeep Kumar

29

Implementation Roll-out plan

Pradeep Kumar

30

Gate 2

Kaviyarasan P

31

The Internal release communication along with all the release artefacts are shared by the Engineering/Product team.

Kaviyarasan P

32

Plan for upgrading the staging/demo instance with the release product - within 2-4 weeks based on the period where no demos are planned from staging for the previous version of the released product.

Pradeep Kumar

33

The Release communication to partners is shared by the GTM team and the Webinar is arranged by the GTM team after the release communication - within 2-4 weeks of the release.