Weekly Project Status Report

Project name  

Documentation @eGov

Week Ending  May 5, 2019
Prepared BySita Bhatt, Rupam Baruah, Mrinalika Akula,Sunita Shelar (25%)
Date PreparedMay 5, 2019

...

Plans For Next Week

  • Creation of new user manuals in BPA -  Document Scrutiny and Approval
  •   Plan documentation activities for May, 2019
  •  




Project Status

Overall


RYGNo major deviation from planned activities as on date

Note:

Green (G) indicates the project is on schedule and there are no major issues.

Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point.

Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project

...

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date
Unplanned formatting tasks asked for by teamsMay derail planned activityRupamAs scheduled by teams
Delays in receiving deliverables from the vendor, lack of design skills within the teamMay delay promotional plans closureSita3-May-2019




Changes To Schedule

StageTarget Completion
Revised CompletionReason
NANANANA

...