Weekly Project Status Report

Project name  

Documentation @eGov

Week Ending  May 5, 2019
Prepared BySita Bhatt, Rupam Baruah, Mrinalika Akula,Sunita Shelar (25%)
Date PreparedMay 5, 2019

...

Accomplishments Of The Week

TechDoc

  1. Creation of a new user manual for Citizen Activities in BPA - Rupam (Click: BPA User Manual - No Objection Certificate)
  2. Updation of Updates to feature list document for HRMS -Rupam (Click: HRMS Feature List Document )

Marketing

  1.  
  2.  
  3.  
Project Management
  1.  
  2.  
  3.  

Knowledge Share, R&D

  1. KT on Confluence Administration - Sunita




Plans For Next Week

  • Creation of new user manuals in BPA -  Document Scrutiny and Approval
  •  
  •  

...

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date
Unplanned formatting tasks asked for by teamsMay derail planned activityRupamAs scheduled by teams
Delays in receiving deliverables from the vendor, lack of design skills within the teamMay delay promotional plans closureSita3-May-2019




Changes To Schedule

StageTarget Completion
Revised CompletionReason
NANANANA

...