Weekly Project Status Report | ||
---|---|---|
Project name | Communications & Content @ eGov | |
Week Ending | August 16, 2019 | |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Praveen Kumar, Neethu Joshwa | |
Date Prepared | August 19, 2019 |
Accomplishments Of The Week | ||
---|---|---|
Pls welcome Neethu Joshwa - Marketing Manager to eGov family. 15 Aug - Holiday Team availability: Sita - connected remotely 3 days, Sita, Neethu - leave 1 day each | ||
Taxonomy
Services & Functional Documentation
| ||
Product Brochures
eGov Internal Newsletter
Awards
Websites
|
...