Weekly Project Status Report | ||
---|---|---|
Project name | Linchpin | |
Week Ending | Week Started: 13 July; 2020, Week ended: 17 July; 2020 | |
Prepared By | Anuj Sachan | |
Date Prepared | 27 July;2020 |
Accomplishments Of The Week | ||
---|---|---|
| ||
Plans For Next Week | ||
---|---|---|
|
Project Status | ||||
---|---|---|---|---|
Overall | R | Y | G | G |
Note: Green (G) indicates the project is on schedule and there are no major issues. Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point. Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project |
Key Issues, Risks, and Concerns | |||||
---|---|---|---|---|---|
Items | Action/Resolution | Responsible | Completion Date | ||
Changes To Schedule | |||||
---|---|---|---|---|---|
Stage | Target Completion | Revised Completion | Reason | ||
...