Weekly Project Status Report | ||
---|---|---|
Project name | Communications & Content @ eGov | |
Week Ending | August 0916, 2019 | |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Praveen Kumar, Neethu Joshwa | |
Date Prepared | August 1619, 2019 |
Accomplishments Of The Week | ||
---|---|---|
New joinee, Pls welcome Neethu Joshwa - Marketing Manager to eGov family. 15 Aug - Holiday Team availability: Sita - connected remotely 5 3 days, Sita, Neethu - leave 1 day each | ||
Technical DocumentationTaxonomy
Services & Functional Documentation
| ||
Marketing Internal CommunicationProduct Brochures
eGov Internal Newsletter
Awards
Websites
|
Plans For Next Week | ||
---|---|---|
Chennai case study - Sita, Neethu Handover/KT - Rupam |