Introduction

Town Planning Schemes masters list contains all building plan approval schemes and sub-schemes available for the benefits of the citizens. Create a list of the available schemes and map these schemes to specific Occupancy Types.

Data Table

Sr. No.

BPA Code

Sub Scheme*

Scheme*

Occupancy Name*Code*

Occupancy Name

1

SCM1

Sub scheme 1 for Ward No. 1

DTP Scheme for Ward No. 1

R1

Residential

SCM2

Sub scheme 2 for Ward No. 1

DTP Scheme for Ward No. 1

C1

Commercial

SCM3

Sub scheme 1 for Ward No. 7

DTP Scheme for Ward No. 7

C1

Commercial

Note: The table above contains sample data for reference.

Procedure

Data Definition

Sr. No.

Column Name

Data Type

Data Size

Is Mandatory?

Description

1

BPA

Code

Alphanumeric

64

Yes

Unique code to record.

2

Sub scheme

Text

256

Yes

Sub scheme name.

3

Scheme

Text

256

Yes

Name of the schemes available at a ULB/state level. This needs to be provided and uploaded into the system so that the same can be applied immediately while processing the permit. 2.

4

Occupancy Code

Alphanumeric

64

Yes

Occupancy code. Refer to Building Occupancy to know more on it.

5

Occupancy Name

Text

64

YesNo

Name provided for occupancy type which is used to configure in the OBPAS modulein Building Occupancy .

Steps to fill data

  1. Download the data template attached to this page.

  2. Refer to the ‘Data Definition’ section of this document to understand the headers in the template sheet, their data type, size, and definitions.

  3. Reach out the person who shared the template for further details or to clear your doubts. Identify the Schemes that exists at a ULB/ State level. Enter the BPA Scheme names.Select the relevant Occupancy Name to map the listed scheme to the selected occupancy typeif the State/ULB has a provision for capturing pipe size for connections.

  4. Identify all the scheme and sub-schemes and fill into given template.

  5. Go through the checklist to verify the data. Make sure that each and every point mentioned in the checklist is covered.

Checklist

The checklist is a set of activities to be performed one the data is filled into a template to ensure data entry requirements are met. These activities have been divided into 2 groups as given below.

Common Checklist

This checklist covers all the activities which are common across the entities.

Sr. No.

Checklist Parameter

Example

1

Make sure that each and every point in this reference list has been taken care of.

Checklist

Entity Specific Checklist

Separate Entity Specific Checklist is not required for this module dataThere is no separate entity-specific checklist for this entity.

Attachments

  1. Configuration Data Template - Town planning Scheme Template

View file
nameTown Planning scheme TemplateConfigurable Data Template - Scheme_V1.xlsx

2. Sample Configuration Data - Town planning Scheme Sample

View file
nameTown Planning scheme Sample.xlsx