Product Release Gate Checklist FSM 1.1

Product Release Gate Checklist FSM 1.1

Sl No

Checklist

Yes/No/ Partially

Reference link

Owner

Remarks

1

Development is completed for all the features that are part of the release.

Yes

High-level features for 1.1 Release

Sathish P

 

2

Test cases are documented by the QA team, reviewed by the product owners and test results are updated in the test cases sheet.

Yes

Test cases

Sathish P



3

The incremental demo of the features showcased during the sprint showcase and feedback incorporated. If possible list out the JIRA tickets for feedback.

No

 

Sathish P

The sprint/release showcase is scheduled for 1st April 2022.

4

UI/UX Audit review by UX Architect is completed along with feedback incorporation for any changes in UI/UX.

Yes

UI/UX Audit Feedbacks

UI/UX Followup Audit

Sathish P

Followup UI/UX audit feedback is done on 31st Mar 2022. Majority of findings are common component observations and will be fixed as part of next release.

5

Incremental demos to the product owners are completed as part of the sprint and feedbacks are incorporated.

Partially



Sathish P

Multiple Incremental demos were completed during the sprint cycle. But there was no end to end to flows are completed.

6

QA signoff is completed by the QA team and communicated to the product owners. All the tickets QA signoff status is updated in the JIRA.

Yes



Sathish P

QA signoff was completed on the 11th of Mar 2022.

7

UI, API Technical documents are updated for the release along with the configuration documents. 

Yes

Tech Docs

Sathish P

These docs will be Published to Gitbook within 2 working days of the release.

8

UAT promotion and regression testing from the QA team is completed. QA team has shared the UAT regression test cases with the product owners.

Yes

Test cases

Sathish P



9

API Automation scripts are updated for new APIs or changes to any existing APIs for the release. API automation regression is completed on UAT, the automation test results are analyzed and necessary actions are taken to fix the failure cases. Publish the list of failure use cases with a reason for failure and the resolution taken to fix these failures for the release.

No

 

Sathish P


QA Automation scripts are not updated for this release.

10

The API backward compatibility testing is completed.

No

DIGIT 2.7 Backward Compatibility Reports

Sathish P

No shared services APIs are changed in the current release for FSM. This release is bundled with the DIGIT 2.7 release and backward compatibility testing is completed for DIGIT 2.7.

11

The communication is shared with the product owners for the completion of UAT promotion and regression by the QA team. The product owners have to give a Product signoff within one week of this communication.

Yes


UAT Escalated issue

Sathish P

UAT regression signoff was completed on the 25th of March 2022.

12

UAT Product Signoff communication is received from the Product owners along with the release notes and User guides (if applicable).

Yes

Release Notes for FSM V1.1

User Manual 

Vyshnavi

Signoff received on 29th Mar 2022.

13

The GIT tags and releases are created for the code changes for the release.

Yes

fsm_v1.1

Sathish P

 

14

Verify whether the Release notes are updated

Yes

Release Notes

Sathish P

 

15

Verify whether all UAT Builds are updated along with the GIT tag details.

Yes

Build and GIT tag details

Sathish P

 

16

Verify whether all MDMS, Configs, InfraOps configs updated.

Yes

Config details

Sathish P

 

17

Verify whether all docs will be Published to http://docs.digit.org by the Technical Writer as part of the release.





Sathish P and Anjoo

These docs will be Published to Gitbook within 2 working days of the release

18

Verify whether all test cases are up to date and updated along with necessary permissions to view the test cases sheet.

Yes

Test cases

Sathish P



19

Verify whether the UAT credentials sheet is updated with the details of new Users and Roles if any

Yes

UAT Credentials

Sathish P



20

Verify whether all the localization data was added in UAT including Hindi and updated in Release Kits.

Yes

Localization - English

Localization - Hindi

Sathish P



21

Verify whether the product release notes and user guides are updated and published

Yes

Release Notes for FSM V1.1

User Manual 

Vyshnavi and Sathish P

 

 

22

The Internal release communication along with all the release artefacts are shared by the Engineering team.

Yes



Sathish P

Shared the Release communication on 31st Mar 2022.

23

The Demo of released features is done by the product team as part of the Sprint/Release showcase.

 

 

Vyshnavi and Sathish P

The sprint/release showcase is scheduled for 1st April 2022.

24

The Release communication to partners is shared by the GTM team and the Webinar is arranged by the GTM team after the release communication - within 2-4 weeks of the release.





 

This will be done by GTM post to the Release communication from Engineering

25

Technical and Product workshops/demos are conducted by the Engineering and Product team based on the need from the implementation team and partners. 





 

The Product and Tech workshop will be arranged after the release communication. Tentative date is 4th to 8th Apr 2022.

26

Plan for upgrading the staging/demo instance with the release product - within 2-4 weeks based on the period where no demos are planned from staging for the previous version of the released product.