Status Report (18th Nov to 22nd Nov)

Weekly Project Status Report

Project name  

BPA- Apply

Week Ending   
Prepared ByPhani & Elzan
Date Prepared25/11/2019

Accomplishments Of The Week

  1. API contract for basic apply is done by Ghanshyam and reviewed by Abhishek. This is been shared with the development team.
  2. Effort estimation for phase 1 is worked out and is coming to Jan 7th for development complete.
  3. Static screen for apply for new construction done and the same was reviewed by Sankar.
  4. tl-services code understanding and exploring on local setup with the eGov team support progressed.
  5. Application Type, Service Type MDMS configuration done locally.
  6. BPA Service setup is done locally.
  7. Application create api is in progress

Plans For Next Week

  1. Share the contract for the remaining features in apply.
  2. Publish the re-worked timelines for development by WT team after adding more people to the team.
  3. Share the sprint plan for the first sprint.
  4. Front End following activities-
    1. Document uploads
    2. NOC Details
    3. including localization
  5. Back End following activities-
    1. Develope application /_create API with the simple flow, without any validations of master data and etc.
    2. All Master data configuration


Project Status

Overall




G

Note:

Green (G) indicates the project is on schedule and there are no major issues.

Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point.

Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date

Changes To Schedule

StageTarget Completion
Revised CompletionReason