eDCR 2020-05-04 Meeting notes

Date- 04th April 2020

 

Participants

  • Manikanta

  • Sanjeev

  • Pradeep

  • Vinoth

 

Goals

Support the Kozhikode on fixing issues.

Discussion topics

Item

Presenter

Tasks are done yesterday

Tasks to be done today

Impediments

Bihar Support on eDCR

Sanjeev

  1. Standardization of Application type / Service Type in edcr

  2. https://digit-discuss.atlassian.net/browse/EDCR-105

https://digit-discuss.atlassian.net/browse/EDCR-105

 

eDCR

Manikanta

Tested filestore service

  1. Move the filestore into UK UAT, if permanent filestore requested is ready

  2. Test and fix backend issues on UK AWS UAT

  3. Study on limitation of NFS

 

eDCR,Client support

Pradeep

  1. BPA design plan and discussion

  2. Story review and estimation for edcr

  3. System configuration meeting

  1. Discussed and finalized the design changes of new bpa rewrite.

  2. BPA Support for pwc on finance and bpa.

  3. Bihar devops discussion with walking tree team.

  4. Prepared eDCR sprint plan

 

Kozhikode Support

Vinoth

  1. Incorporate Regularization permit order format changes due to amendment

  1. Testing a checklist based on the amendment date

  2. Enable online permit usage fee and testing

  3. Enable services in portal and testing

 

Action items

 

Decisions