eDCR 2020-05-08 Meeting notes

Date- 08th April 2020

 

Participants

  • Manikanta

  • Sanjeev

  • Pradeep

  • Vinoth

 

Goals

Support the Kozhikode on fixing issues.

Discussion topics

Item

Presenter

Tasks are done yesterday

Tasks to be done today

Impediments

Bihar Support on eDCR

Sanjeev

  1. MDMS integration and support to integrate application type and service type from mdms

  2. Appraisal discussion

  3. All hands meet

MDMS initial integration with edcr

 

eDCR

Manikanta

  1. edcr gate discussion

  2. Appraisal discussion

  3. All hands meet

  4. DCR design changes continue plan

  5. Might initiate work on Open Stack Swfit based on Dhananjays confirmation

 

 

eDCR,Client support

Pradeep

  1. Appraisal discussion

  2. Team restructure discussion

  3. All hands meet

  4. Digit BPA stories sprint discussion

  1. Support Bihar team on the portal.

  2. Appraisal discussion with elzan,seema,sanjeev and vinoth.

 

Kozhikode Support

Vinoth

  1. regularization changes

  2. Appraisal discussion with Sanjeev

  3. All hands meet

  4. Accessory building rule no and description updation for amendment

  1. Appraisal discussion with Seema and Pradeep.

  2. KOZHIKODE-1064 Corrected required values as per rule in the rear yard

  3. KOZHIKODE-1065 Update rule no and change non-notified to un-notified
    in accessory block

  4. KOZHIKODE-1064 change or to and condition in rear yard when checking
    side yard values

  5. KOZHIKODE-1066 fixed the reset password not working

 

 

Action items

 