Communications & Content Status Update - 21 April'19
Weekly Project Status Report | ||
|---|---|---|
| Project name | Communications & Content | |
| Week Ending | April 21, 2019 | |
| Prepared By | Sita Bhatt, Rupam Baruah, Sunita Shelar (25%) | |
| Date Prepared | April 22, 2019 | |
Accomplishments Of The Week | ||
|---|---|---|
Note: Rupam was on leave on Wed, and Thurs/Fri were holidays at eGov. TechDoc
Marketing 3. AP video content identified and shared - Sita 4. Whitepaper design coordination with agency - Sita 5. Videos for investor meet delivered - Sita Product Management 6. PhraseApp trial version received after the initial conversation with the company representative - Sita Project Management 7. Test for Graphic Designer - Sita 8. Detailed Ops plan for Content and Communications created and reviewed - Sita 9. Followup for senior TechDoc writer and onboarding - Sita |
Plans For Next Week | ||
|---|---|---|
|
Project Status | ||||
|---|---|---|---|---|
| Overall | R | Y | G | No major deviation from planned activities as on date |
Note: Green (G) indicates the project is on schedule and there are no major issues. Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point. Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project | ||||
Key Issues, Risks, and Concerns | |||||
|---|---|---|---|---|---|
| Items | Action/Resolution | Responsible | Completion Date | ||
| Unplanned formatting tasks asked for by teams | May derail planned activity | Rupam | As scheduled by teams | ||
Changes To Schedule | |||||
|---|---|---|---|---|---|
| Stage | Target Completion | Revised Completion | Reason | ||
| None | NA | NA | NA | ||