Communications & Content Status Update - 24 May'19

Weekly Project Status Report

Project name  

Communications & Content @ eGov

Week Ending  May 24, 2019
Prepared BySita Bhatt, Rupam Baruah, Mrinalika Akula, Rohan Prasad, Sunita Shelar (25%), Parth Madan (10%)
Date PreparedMay 27, 2019

Accomplishments Of The Week

  • The Ken - 15 subscriptions for 1 year delivered for the leadership team and identified team members - Sita
  • Translation activity for more than 2610 strings, consisting of 2,3-4 literals per string, initiated through Upwork, cost-saving of 13 INR per literal . View source sheet here - Sita, Prashant
  • Various DIGIT artifacts from Platform team are migrated to eSankalan. These documents include release notes, API details for various services of DIGIT, training PPTs, service YAMLs and more. To view the artifacts in eSankalan, Click here - Rupam, Rohan
  • eSankalan space for Andhra Pradesh team is created along with basic TOC and has been shared to the concerned team. To view AP team space, Click here - Rupam

TechDoc

Mrinalika leave - 1 day

Rohan - 2 weeks internship closure

  1. Release Notes (Click : Template) and Feature List (Click: Template) updated - Rupam
  2. Billing and Collection Service API document updated on eSankalan for engineering team (Click:Integration Doc) - Rupam
  3. Platform Team shared artifacts for DIGIT, uploaded documents and finalized the eSankalan page (Click: DIGIT Artifacts) - Rupam, Rohan
  4. Learning session and review of new documentation templates in eSankalan like Release Notes, User Manuals with AP and Product Management team - Rupam, Mrinalika, Sita 
  5. UserManual-Universal Collections reviewed and enhanced the contents - Mrinalika
  6. Circulated the first draft of screens layout for user Manuals for Review and initiated Common Features User Manual CommonFeatures_UserManual - Mrinalika
  7. Planning for mSeva documentation and help files - Mrinalika, Sita, Rupam, Sunita
  8. eSankalan newsletter draft, review - Sita, Rupam, Mrinalika
  9. Content and Communications deep-dive document creation - Sita, Sunita
  10. Glossary update - Rohan. Sita
  11. mSeva -Walkthrough of phase 1 functionality by Product Management team - Rupam, Mrinalika

Marketing

  1. Contact@egovernments.org queries from citizens addressed: 1 for AP, 1 for Chennai, 1 for Punjab, 1 general query to HR, 1 training workshop invite for Chennai - Sita
  2. Rohan (intern) readiness to attend to eSankalan tasks addressed - email ID creation, KT for Confluence, handover of internship certificate, closure of internship - Rupam, Sita, Shahid
  3. Content gathering for the external email newsletter - Sita
  4. Screening of 7 Marketing Lead profiles: 1 interview completed-rejected due to low verbal communication skills, 1 no-show - Sita, Shahid, Himani
  5. Screening of 2 Graphic Design profiles: 1 rejected due to lack of experience - Sita, Shahid, Himani
  6. Cleanup of 407 mail IDs with first, last name details based on cards available. Physical alphabetical sorting of cards completed- this was not done by earlier owner. The rest of the 1486 IDs are unverified as we don't have the cards - Rohan, Sita
  7. Impact film testing and availability for All Hands Meet - Sita, Tufail

Plans For Next Week

  • Documentation activity for Fire NOC and Universal Collections (The documentation output will be the feature list, release notes and user manuals for employee and/or citizen)
  • Glossary launch and Platform artifacts availability through eSankalan newsletter
  • Translation completion English-Hindi for Rainmaker 
  • Interviews for Marketing Lead and Graphic Designer
  • Review of OKRs, prioritization of documentation artifacts
  • External newsletter finalization for release
  • Impact film (yet not received from vendor) promotion activities
  • Whitepaper (yet to be released, held back due to MIT logo confirmation) promotion activities

Project Status

Overall


RYGG

Note:

Green (G) indicates the project is on schedule and there are no major issues.

Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point.

Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date
Vendors delay on impact film and white paperDaily follow-upSita31 May'19

Changes To Schedule

StageTarget Completion
Revised CompletionReason
None as of now