Egov API Automation :: Weekly Status :: 25/01-29/01

Tasks/Accomplishments:

  • Connected with the dev team for the TC’s review.

  • automation karata-master build tested with 170 TCs with 99% Pass rate.

Tasks

Weekly Status

Percentage

Comments

Manual Test Cases: egov-access-control

Done

100%



Manual Test Cases: workflow service

Done

100%

 

Manual Test Cases:

url shortening

Done

100%

 

Manual Test Cases:

Dashboard Ingest

On Hold

20%

explored save,upload and migrate end points.

Getting an error in all the above API, will be taking this up next week.

 

Automation: pb UAT url update

InProgress

40%

Have not worked on it this week.

Automation : Billing-Services-Bill-fetchBill

Done

100%

Merged with karate-master

Automation: billing-service-demand

Done

100%

 

Automation: pdfservice

Done

100%

 

Automation:
apportion-service

Done

95%

Ready for review

Automation:
Dashboard Analytics

Done

95%

Ready for review

Automation:
enc-service

InProgress

90%

will complete by EOD
29/01/2021

Automation: billing-service

Done

100%

 

egov-mdms-service

InProgress

70%

Scripting is completed and tested but need some more clarity on baseUrl of environment. Currently pending for clarification

eGovWorkFlow

InProgress

60%

Will complete it by EOD

 

Discussions/Action Items:  

  • Automation Karate Master branch (karate-master) handover complete for review as on 21-01-2021 with stable test suite.

  • Approach Document initial draft submitted, reviewed and automation team to work on test suit building to ensure kafka framework for DIGIT services

  • automation team is mitigating code changes to ensure “Platform independency and dynamic data usage” in test automation suits.

  • CICD configuration is progressed