Egov API Automation :: Weekly Status :: 25/01-29/01
Tasks/Accomplishments:
Connected with the dev team for the TC’s review.
automation karata-master build tested with 170 TCs with 99% Pass rate.
Tasks | Weekly Status | Percentage | Comments |
Manual Test Cases: egov-access-control | Done | 100% | |
Manual Test Cases: workflow service | Done | 100% |
|
Manual Test Cases: url shortening | Done | 100% |
|
Manual Test Cases: Dashboard Ingest | On Hold | 20% | explored save,upload and migrate end points. Getting an error in all the above API, will be taking this up next week.
|
Automation: pb UAT url update | InProgress | 40% | Have not worked on it this week. |
Automation : Billing-Services-Bill-fetchBill | Done | 100% | Merged with |
Automation: billing-service-demand | Done | 100% |
|
Automation: pdfservice | Done | 100% |
|
Automation: | Done | 95% | Ready for review |
Automation: | Done | 95% | Ready for review |
Automation: | InProgress | 90% | will complete by EOD |
Automation: billing-service | Done | 100% |
|
egov-mdms-service | InProgress | 70% | Scripting is completed and tested but need some more clarity on baseUrl of environment. Currently pending for clarification |
eGovWorkFlow | InProgress | 60% | Will complete it by EOD |
Discussions/Action Items:
Automation Karate Master branch (karate-master) handover complete for review as on 21-01-2021 with stable test suite.
Approach Document initial draft submitted, reviewed and automation team to work on test suit building to ensure kafka framework for DIGIT services
automation team is mitigating code changes to ensure “Platform independency and dynamic data usage” in test automation suits.
CICD configuration is progressed