Egov API Automation :: Weekly Status :: 12/04-16/04

Tasks/Accomplishments:

  • Completed creating manual Test cases for E2E-BPA and sent to the product team for review.

  • Completed Automation of Land-Services.

 

Tasks

Weekly Status

Percentage

Comments

Manual Test Cases: e2e BPA

In Review

95%

 

Manual Test Cases: PGR Service

In-progress

20 %

 

Automation:
enc-service

In-progress

90%

encryption is working fine. Decrypt & Rotate api’s are failing. Awaiting input from Tarun

Automation:

noc-services

In-Review

95%

 

Automation:

kafka related test cases

In-Progress

60%

 

Automation:

land-services

In-Progress

100%

 

Automation:

Fire-Noc

In-progress

30%

 

Automation:

DCR-Service

In-Progress

70%

 

Automation:
Fire NOC Billing Slab

In-Progress

10%

 

 

Discussions/Action Items/Risks:

  • Since there is unavailability of a SDET due to medical emergency ,  there will be delay in completion of planned tasks in the current sprint. The automation plan to be re-assessed.