Egov API Automation :: Weekly Status :: 19/04-23/04

Tasks/Accomplishments:

  • Manual Test cases for e2e-pgr, egov-Pdf ,user-events and e2e-Firenoc are progressed

  • Automation: DCR-Service & noc-servies are InReview

  • Automation : fire-Noc & fire-Noc billing slab are In Progress

 

Tasks

Weekly Status

Percentage

Comments

Manual Test Cases: e2e BPA

Done

100%

 

Manual Test Cases: PGR Service (e2e)

In-review

95 %

 

Manual Test Cases: e2e-Firenoc

In-progress

60%

 

Manual Test Cases: egov-pdf

Done

100%

 

Manual Test Cases: egov-user-events

In-Review

95%

 

Automation:
enc-service

In-progress

90%

encryption is working fine. Decrypt & Rotate api’s are failing. Awaiting input from Tarun

Automation:

noc-services

In-Review

95%

This is to be reviewed by Yatheendra. Since he is unavailable, the status is same.

Automation:

kafka related test cases

In-Progress

60%

Samay has taken this up now as he was on leave last week.

Automatioocn:

Fire-Noc

In-progress

80%

 

Automation:

DCR-Service

In-Review

95%

 

Automation:
Fire NOC Billing Slab

In-Progress

70%

 

 

Discussions/Action Items/Risks:

  • Since there is unavailability of a SDET due to medical emergency ,  there will be delay in completion of planned tasks (e2e-BPA) in the current sprint. The automation plan to be re-assessed.