QA Automation :: Weekly Status :: 12/07-16/07
Tasks/Accomplishments:
Manual Test cases are progressed for Trade Licence
Tasks | Weekly Status | Percentage | Comments |
Manual Test Cases: e challan UI | Done | 100% |
|
Manual Test Cases: HRMS | In-Review | 90 % | QA review in progress |
Manual Test Cases: PT | In-Review | 90% | QA review in progress |
Manual Test Cases: Receipt Cancellation | In-Review | 90% | QA review in progress |
Manual Test Cases: TL | In-progress | 70% |
|
Automation: | In-progress | 90% | encryption is working fine. Decrypt & Rotate api’s are failing. Awaiting input from Tarun |
Automation: | In- Progress | 95% | Blocked with File Upload. Working on it. Since Samay is on PTO, this will be taken up next week |
Automation: FireNoc And FSM (API review comments update) | Done | 100% |
|
FSM UI Automation | Done | 100% |
|
Automation: Demo Comments | InProgress | 90% | Blocked due to the memory issue, working fine with 16gb or above RAM |
Automation: State Level Customisation | InProgress | 60% | Blocked: facing issue to resolve in karate framework |
Automation: Rectify and Decrease Automation Script Failures | inProgress | 20 % |
|
Automation: mCollect web and mobile | InProgress | 30% |
|
Discussions/Action Items/Risks:
Risk- Rectify and Decrease Automation Script Failures are 196 scripts. it is not possible to fix in two day.
Risk - State level customisation, executing the whole regression suite and upload functionality is blocked due to inconsistency/lack of support in karate framework