Planned Tasks

Delivered Tasks

Comments

Planned Tasks

Delivered Tasks

Comments

Preparation of manual test cases :

  • Localisation

  • Userotp

  • Filestore

Delivered all tasks:

  • Localisation

  • Userotp

  • Filestore

 

Preparation of automation test cases :

  • Localisation

  • Userotp

  • Filestore

Status as below:

  • Localisation - Delivered

  • Userotp - 90% Done

  • Filestore - Did not start

Userotp - Kafka approach related tests are pending.

Most time we spent on framework level fixes as and when we started with tech reviews.

An approach on how Consumers and Producer based APIs will be tested

No

Help required on the Kafka process and the approach to fix it from the developer.

Document all the test case for Phase 1 and Phase 2

Phase 1 - Started

Phase 2 - Not started

  • Total 27 Services and 72 Endpoints

  • Below is the phase 0 status of endpoints test cases:

  • Done - 17
    Deprecated - 7
    Need clarifications - 20
    Test cases pending - 28

  • Most of the time we spent on analysis and follow up with team to understand the functionality, status of endpoints etc. Due to that we were unable to pick up Phase 2 planned test cases.

Decide on Phase 1 milestones and services order

Reordered based on the information we are getting and proceeding with the same.

Test strategy document has mentioned 27 services with 9 Milestones.

Get sign off on POC and test cases for proceeding to Phase 1.

Pending

 

 

Phase 1

Phase Start Date : 9th Dec 2020

Phase End Date : 2nd March 2021

Sprint 2 - In Progress

Preparation of manual test cases :

Milestone 1:

  • HRMS

  • Pg.Service

  • Pdf.Service

Milestone 2:

  • egov-searcher

  • egov-reports

  • egov_user

Milestone 3:

  • egov-accesscontrol

  • egov-mdms-service

  • egov-enc-service

 

Status as below:

Milestone 1:

  • HRMS - Done

  • Pg.Service - Done

  • Pdf.Service - Done

Milestone 2:

  • egov-searcher - Done

  • egov-reports - Done

  • egov_user - Done

Milestone 3:

  • egov-accesscontrol - In Progress

  • egov-mdms-service - Done

  • egov-enc-service - In Progress

Sprint 2 is in progress.

 

Preparation of automation test cases :

Milestone 1:

  • egov-idgen

  • egov-location

  • egov-mdms-service

Milestone 2:

  • egov-reports

  • egov-searcher

  • hrms

Status as below:

  • Localisation - Done

  • Filestore - 90% Done

Milestone 1

  • egov-idgen

  • egov-location

  • egov-mdms-service

Milestone 2

  • egov-mdms-service - In Progress

  • egov-searcher - In Progress

  • hrms - In Progress

Sprint 2 is in progress

Filestore - multipart file upload 2 tests are pending as technical workaround to be found.