Weekly Project Status Report

Project name  

Communications & Content @ eGov

Week Ending  July 26, 2019
Prepared BySita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%)
Date PreparedJuly 26, 2019


Accomplishments Of The Week


Team Availability

Mrinalika on leave - 2 days

Technical Documentation 

  • The initial draft of the document on the eGov documentation publishing framework - Click here - Rupam
  • Documentation on eGov and DIGIT website defect list - Click here - Rupam
  • Incorporation of SME Review comments for Fire NOC feature list - Click here - Rupam
  • Drafted first cut content for PGR brochures for leadership review - Mrinalika 

eSankalan

Marketing


Plans For Next Week

    • Billgenie documentation - Rupam

...