Automation team last moment finished all tests assignedPreparation of test scripts and execution were completed before deadline.Test Creation for Phase 0 services were completed as plannedThanks to Srishti for providing the data with a quick turn around

Tester

What went well?

What didn’t go well?

Improvements/Learnings

Hamsa

Test Creation for Phase 0 services were completed as planned

Hamsa

Good Team work

Sarita

Preparation of test scripts and execution were completed before deadline.

Shareef

Finished test scripts and execution before deadlines

Shareef

KT on different modules

Hamsa

Thanks to Srishti for providing the data with a quick turn around

Hamsa

Some of the API's (ex: Localistion, Otp) were not working on QA environment

Shareef

Karate framework

Shareef

Naming conventions in framework

Shareef

How to add test scripts in karate framework

Good Team work

Domain Knowldge

KT on different modulesSarita

Continue adding the questions in the questions/ clarifications sheet more proactively

Hamsa

KT's can be more organised

Hamsa

Early feedback on TC's would be helpful

Hamsa

Action Items

Team has to setup Test case review meeting and fix all the review comments before automating the TCs

Get complete information on the topics for KT with SMEs before scheduling a session. Work with Dharma on that to get clear information.

Send an email to follow up after the TC's review comments are incorporated

Shan to ask Nikesh to create a automation group so that the team can send emails to the group

Meetings to be scheduled for 25 mins / 50 mins instead of 30mins/ 60mins

Testers can exlpore on UAT too as long as its only transcations. Avoid updating configurations on UAT

...