Date | 25-1-2020 |
---|---|
Team | Egov Automation |
Participants | Pundaleek H (Unlicensed) Sathish P Sarita Mohapatra Shareef Shaik Tarun Lalwani Bhavana Vasudev Shanmugam Moorthy |
Tester | What went well? | What didn’t go well? | Improvements/Learnings |
---|---|---|---|
Automation team last moment finished all tests assigned | Some of the API's (ex: Localistion, Otp) were not working on QA environment | Karate framework | |
Preparation of test scripts and execution were completed before deadline. | Naming conventions in framework | ||
Test Creation for Phase 0 services were completed as planned | How to add test scripts in karate framework | ||
Good Team work | Domain Knowldge | ||
KT on different modules | Continue adding the questions in the questions/ clarifications sheet more proactively | ||
Thanks to Srishti for providing the data with a quick turn around | KT's can be more organised | ||
Early feedback on TC's would be helpful |
Action Items
Team has to setup Test case review meeting and fix all the review comments before automating the TCs |
Get complete information on the topics for KT with SMEs before scheduling a session. Work with Dharma on that to get clear information. |
Send an email to follow up after the TC's review comments are incorporated |
Shan to ask Nikesh to create a automation group so that the team can send emails to the group |
Meetings to be scheduled for 25 mins / 50 mins instead of 30mins/ 60mins |
Testers can exlpore on UAT too as long as its only transcations. Avoid updating configurations on UAT |
Refer: Link