Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.



Weekly Project Status Report

Project name  

Documentation @eGov

Week Ending  April 28, 2019
Prepared BySita Bhatt, Rupam Baruah, Sunita Shelar (25%)
Date PreparedApril 29, 2019

...

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date
Unplanned formatting tasks asked for by teamsMay derail planned activityRupamAs scheduled by teams
Delays in receiving deliverables from the vendor, lack of design skills within the teamMay delay promotional plans closureSita3-May-2019




Changes To Schedule

StageTarget Completion
Revised CompletionReason
NANANANA

...