Tasks/Accomplishments:
Completed Phase 2 planning - reviewed and approved by eGov.
Manual test cases for phase 1.1 items and muncipal services- phase 2 are progressed
Team started connecting with product team for E2E scenarios review
Tasks | Weekly Status | Percentage | Comments |
Manual Test Cases: Accountdetailstype (egf-master) | Done | 100% | |
Manual Test Cases: Property Services | In-progress | 90% | In Review |
Manual Test Cases: E2E for property Module | In-progress | 30 % | |
Manual Test Cases: | |||
Automation: | Completed | 100% | |
Automation: | In-progress | 80% | since apportion service was not working even after role mapping, we had kept it on hold. we’ll do the role mapping for it |
eGovUser(new testcases) | Completed | 100% | |
Automation: | Completed | 100% | |
Automation: | Completed | 100% | |
Automation: dashboard-ingest | Completed | 100% | |
Automation: egf-master: bankbranches | In Progress | 40% | |
Testing kafka rest proxy configuration on QA | Completed | 100% | |
Automation: | Completed | 100% | |
Automation: | Completed | 100% |
Discussions/Action Items: