Weekly Project Status Report |
---|
Project name | Communications & Content @ eGov |
Week Ending | June 7, 2019 |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Parth Madan (25%) |
Date Prepared | June 7, 2019 |
Accomplishments Of The Week |
---|
- Creation and review of the first draft for Fire NoC release notes, citizen user manual - Rupam
|
TechDoc |
Rupam leave - 1 day, Holiday - 1 day |
eSankalan - Published eSankalan newsletter to all of eGov - Rupam, Mrinalika, Sita
- Creation of the first draft for Fire NoC release notes - Rupam (Click here)
- Creation of the first draft for Fire NoC citizen user manual - Rupam (Click here)
|
Marketing |
Plans For Next Week |
---|
- Planned User Manual, Release Notes and Feature List delivery for Universal Collections - delayed as base content is planned to be delivered from Product Manager by 31 May'19.
- Planned User Manual, Release Notes and Feature List creation for Fire NOC
- Planned API Documentation and Integration diagrams for Universal Collections & Fire NOC. Review post creation by Engineering team and readiness for publishing
- Roll out of monthly newsletter to partners, funders and government officials
|