Weekly Project Status Report |
---|
Project name | Communications & Content @ eGov |
Week Ending | June 21, 2019 |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Parth Madan (10%) |
Date Prepared | June 24, 2019 |
Accomplishments Of The Week |
---|
- A one-stop repository of emails, communications, policy documents and other artifacts for eGovernments Administration Team- Rupam Click to view
|
Team Availability |
Sita working with remote access - 1 day, Mrinalika - 1-day leave |
eSankalan - Collation of all artifacts from Google drives including release notes, user manuals, learning videos, master data collected on the ground, marketing content; creation of Punjab-DIGIT implementation and upload of existing artifacts, reviews and rework - Rupam, Sita
- End to end KT to eGov Implementation team (Nabina) on eSankalan along with hands-on examples on file uploads/downloads, creating new content, maintenance activities, tagging activities, etc. - Rupam
- Creation of eGovernments Administration space and uploaded artifacts as organizational policy documents, official communications, etc. Click here - Rupam
- The first draft of release notes for Fire NOC application Click here - Rupam, Sunita
- The first draft of the citizen user manual for Fire NOC application (WIP) Click here - Rupam
|
Marketing |
Plans For Next Week |
---|
- Planned User Manual, Release Notes and Feature List creation for Fire NOC
- Planned API Documentation and Integration diagrams for Universal Collections & Fire NOC. Review post creation by Engineering team and readiness for publishing
|