04-11-2020 Standup notes

Date

04-Nov-2020

Participants

@Dhananjay Singh @Ramakrishna Ippili @Aayush Sharma @Ghanshyam Rawat @Narendra Bandhamneni (Unlicensed) @Tarun Lalwani

Goals

  • Daily Stand up discussions

Discussion topics

Item

Presenter

Notes - Previous day

Notes - Current day

Notes - impediment

Item

Presenter

Notes - Previous day

Notes - Current day

Notes - impediment

Backend

Ghanshyam

 

  • Tested PT migration, reached to 5 hrs migration time, came across data issues

  • When tried both PT and Collection, kafka went down

  • by EOD coming Friday able to give both the migration which can complete in 5hrs

 

Backend

Ramki

 

  • Did PT and collection migrations on UAT V2 instance with old migration builds

  • Reported some data issues to Ghanshyam and Kavi

  • Added ticket to restore PB prod DB on PB QA environment

 

Action items

Decisions