Weekly Project Status Report |
---|
Project name | Communications & Content @ eGov |
Week Ending | May 31, 2019 |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Parth Madan (10%) |
Date Prepared | May 31, 2019 |
Accomplishments Of The Week |
---|
- Various DIGIT artifacts from AP team are migrated to eSankalan. These documents include SRS document, user manuals on Asset Management, Property Tax, Water Charges, etc. for Andhra Pradesh DIGIT implementation. To view the artifacts in eSankalan, Click here - Rishi, Rupam
- Deep dive meet on Documentation OKR and finalization on timeline and deliverables - Sita, Sunita, Rupam, Mrinalika
- An eSankalan page for engineering team on Integration document of DIGIT services with the third party for Water and Sewage. To view, Click here - Rupam
|
TechDoc |
- Updation of Platform Documentation page (Click here) with the upload of Docx, PDF, and hyperlinks for every document - Rupam
- Billing and Collection Service API document updated on eSankalan for engineering team (Click:Integration Doc) - Rupam
- Glossary update - Mrinalika, Sita
|
Marketing |
Plans For Next Week |
---|
- Documentation activity for Fire NOC and Universal Collections (The documentation output will be the feature list, release notes and user manuals for employee and/or citizen)
- Glossary launch and Platform artifacts availability through eSankalan newsletter
|
Project Status |
---|
Overall
| R | Y | G | G |
Note: Green (G) indicates the project is on schedule and there are no major issues. Yellow (Y) means the project is somewhat delayed and/or there may be some major risks at the current point. Red (R) means the project is seriously at risk of being delayed and/or there are some major risks affecting the project |
Key Issues, Risks, and Concerns |
---|
Items | Action/Resolution
| Responsible | Completion Date
|
|
|
|
|
Changes To Schedule |
---|
Stage | Target Completion
| Revised Completion | Reason
|
None as of now |
|
|
|