Weekly Project Status Report

Project name  

Communications & Content @ eGov

Week Ending  May 10, 2019
Prepared BySita Bhatt, Rupam Baruah, Mrinalika Akula,Sunita Shelar (25%)
Date PreparedMay 10, 2019

...

Key Issues, Risks, and Concerns

ItemsAction/Resolution
ResponsibleCompletion Date
Unplanned formatting tasks asked for by teamsMay derail planned activityRupamAs scheduled by teams
Delays in receiving deliverables from the vendor, lack of design skills within the teamMay delay promotional plans closure and other design deliverablesSita


Changes To Schedule

StageTarget Completion
Revised CompletionReason
NANANANA

...