Linchpin - eGov UI Revamp (Ipsator)
Driver | Approver | Contributors | Stakeholder |
---|---|---|---|
@Anuj Sachan | @Abhinav Kushwaha | @Abhinav Kushwaha |
|
Objective | eGov UI Revamp |
Due date | Sep 15, 2020 |
Key outcomes | Redesign of UI |
Status | STARTED |
Problem Statement
Scope
Must have:
Phase 1 - micro-frontend framework + UI component library + PGR module
Phase 2 - Core app framework + UI component updates + mcollect and other modules
Milestones and deadlines
Milestone | Owner | Deadline | Status |
---|---|---|---|
Final design for v1 | @Abhinav Kushwaha | 31 july: 2020 | NOT STARTED |
PGR Review | @Abhinav Kushwaha | 30 August; 2020 | NOT STARTED |
mCollect Review | @Abhinav Kushwaha | 30 September 2020 | NOT STARTED |