Phase 2.1: Sprint 1 (03 Mar- 16 Mar)

Participants: @Sathish P @Tarun Lalwani @Bhavana Vasudev @Krishnendu Halder @Yatheendra BC @Hamsa Nandini

 

Tester

What went well?

What did not go well?

Improvements / Learnings

Tester

What went well?

What did not go well?

Improvements / Learnings

Hamsa

Completed manual test cases as planned

 

  1. mCollect

Yatheendra

Completed writing automation scripts for all the assigned service

Contribution to kafka implementation in our automation framework

Gained some knowledge on kafka workflow process

Krishnendu

  1. Able to complete major assigned tasks on time

  2. Good collaboration with team

Delayed automation for End to End property flow and dragged into next sprint plan

Gained knowledge on property-calculator service endpoints