Linchpin - eGov UI Revamp (Ipsator)

Driver

Approver

Contributors

Stakeholder

Driver

Approver

Contributors

Stakeholder

@Anuj Sachan

@Abhinav Kushwaha

@Abhinav Kushwaha

 

Objective

eGov UI Revamp

Due date

Sep 15, 2020 

Key outcomes

Redesign of UI

Status

STARTED

Problem Statement

Scope

Must have:

  • Phase 1 - micro-frontend framework + UI component library + PGR module

  • Phase 2 - Core app framework + UI component updates + mcollect and other modules

https://docs.google.com/spreadsheets/d/11il3K-mgJIX5JX4CKnwAwKYWhqBNW6L5IJArrviN42M/edit?ts=5efc72d3#gid=0
29-Jun202006-Jul13-Jul20-Jul27-Jul03-Aug10-Aug17-Aug24-Aug31-Aug07-Sep14-Sep21-Sep28-SepStart
Architect
Architect +2Dev

Framework Design Phase-1

Framework Design Phase-2

Interoperability and Deployment

Core App Rewrite

UI Elements & Component Lib

PGR UI Flows

PGR Module (UI And API Integration)

UI Flows

MCollect and other modules

Milestones and deadlines

Milestone

Owner

Deadline

Status

Milestone

Owner

Deadline

Status

Final design for v1

@Abhinav Kushwaha

31 july: 2020

NOT STARTED

PGR Review

@Abhinav Kushwaha

30 August; 2020

NOT STARTED

mCollect Review

@Abhinav Kushwaha

30 September 2020

NOT STARTED