Egov API Automation :: Phase 0:: Deliverable
@Sathish P @Tarun Lalwani @Hamsa Nandini @Shanmugam Moorthy @Sarita Mohapatra @Shareef Shaik @Bhavana Vasudev
Sprint Start Date : 11 Nov 2020
Sprint End Date : 8 Dec 2020
Phase 0 Goals:
Preparation of test cases for user_otp
Preparation of test cases for localization
Automate egov localization APIs
Manual Test Cases for Phase 1 and Phase 2 are planned.
Total 27 Services and 72 Endpoints
Below is the current status of endpoints test cases:
Done - 17 Deprecated - 7 Need clarifications - 20 Test cases pending - 28
Automation Planned as below
Localisation - Done
Userotp - Done
Filestore - Pending
Deliverable:
Automation Test Report