Egov API Automation :: Weekly Status :: 22/03-26/03

Tasks/Accomplishments:

  • Manual Test cases are progressed for BPA and PGR services.

  • Automation of ws-services, ws-calculator, sw services and tl-calculator are completed.

Tasks

Weekly Status

Percentage

Comments

Manual Test Cases:

BPA Service

In-Progress

90%

Ready for Review

Manual Test Cases:

BPA Calculator

In-Progress

50%

Getting an error in the API, checking with dev

Manual Test Cases:

PGR-Service

 

In-Progress

90 %

Ready for Review

Manual Test Cases:

Land Services

In-Progress

90 %

Ready for Review

Manual Test Cases:

noc-services

In-Progress

10 %

Pulled from the backlog of future sprints since BPA E2E is dependent on it.

Automation:
enc-service

In-progress

90%

encryption is working fine. Decrypt & Rotate api’s are failing. Awaiting input from Tarun

Automation(kafka):

egov-persister

In-Progress

80%

kafka implementation is completed this week. will be taken up next sprint

Automation: zool / telemetry

Done

100%

 

Automation:

End to End test of PT

In-Progress

70%

Converted all manual end to end test cases into automated tests but we need to revisit again once payment gateway related step handled by test framework

Automation:

End to End test of mCollect

Done

100%

 

Automation:

propertytax/_estimate
propertytax/_calculate

Done

100%

 

Automation:

billingslab/_create
billingslab/_search

Done

100%

 

Automation:

ws-services/wc/_search

Done

100%

 

Autoamtion:

ws-services/wc/_create ws-services/wc/_update

Done

100%

 

Automation:

ws-calculator

Done

100%

 

Automation:

sw-services

Done

100%

 

Automation:

sw-calculator

In-Progress

40%

 

Automation: WS End to End

In-Progress

40%

 

Automation: TL-Services

In-Progress

80%

 

Automation: TL-Calculator

In-Progress

90%

Ready for Review

Automation:

End to End test of TL

In-Progress

20%

 

 

Discussions/Action Items:

  • Kafka Implementation is approved by Tarun with 2 final review comments which are also addressed and completed

  • Take up the kafka related service test cases in next sprint - (persister, indexer,notification sms/email)

  • Automation Handover - Will be given hand over to implementation team once the QA team confirms

  • Payment gateway API’s will not be a part of the upcoming Digit release (Mar-31). A separate email has been shared to Sathish regarding this.

  • Manual test cases on noc-services is pulled from the backlog of future sprints since BPA E2E is dependent on it.

  • Manual TC’s for BPA-E2E will be taken up in the upcoming sprint.