QA Automation :: Weekly Status :: 16/08-20/08
Tasks/Accomplishments:
Tasks | Weekly Status | Percentage | Comments |
Manual Test Cases: HRMS | In-Review | 90 % | QA review in progress |
Manual Test Cases: PT | In-Review | 90% | QA review in progress |
Manual Test Cases: Receipt Cancellation | In-Review | 90% | QA review in progress |
Manual Test Cases: TL | In-Review | 90% | QA review in progress |
Manual Test Cases: Fire Noc | On Hold | NA | This is removed from the priority and BPA was taken instead. Mocks are WIP by the product team. |
Manual Test Cases: BPA new UI | In-progress | NA | Employee Design is WIP by the product team |
Manual Test Cases: Bill Amendment, W&S , Bill Genie | In-progress | NA | Mocks are WIP by the product team. |
Discussions/Action Items/Risks:
QA Test Case Review is taking longer than expected. Team is busy with release work.
Hamsa is also helping the internal SDET’s for UI automation.