QA Automation :: Weekly Status :: 05/07-09/07
Tasks/Accomplishments:
Manual Test cases are progressed for receipt cancellation and PT
FSM UI automation is completed.
FSM and Firenoc apis code modification is completed.
Tasks | Weekly Status | Percentage | Comments |
Manual Test Cases: PGR UI | Done | 100% |
|
Manual Test Cases: FSM UI | Done | 100% |
|
Manual Test Cases: e challan UI | In-Review | 95% | Product team review pending |
Manual Test Cases: HRMS | In-Review | 90 % | QA review in progress |
Manual Test Cases: PT | In-Progress | 85% |
|
Automation: | In-progress | 90% | encryption is working fine. Decrypt & Rotate api’s are failing. Awaiting input from Tarun |
Automation: | In- Progress | 95% | Blocked with File Upload. Working on it. Since Samay is on PTO, this will be taken up next week |
Automation : PGR UI | Done | 100% |
|
Automation: FireNoc And FSM (API review comments update) | Done | 100% |
|
FSM UI Automation | Inprogess | 25% |
|
Discussions/Action Items/Risks:
2.5 Digit release for QA automation will include only API automation and a release documentation for the same has been shared with the eGov team. UI automation to be included in the future releases.
Latest Automation Code (API changes) is merged to master.