Communications & Content Status Update - 7 June'19
Weekly Project Status Report | ||
---|---|---|
Project name | Communications & Content @ eGov | |
Week Ending | June 7, 2019 | |
Prepared By | Sita Bhatt, Rupam Baruah, Mrinalika Akula, Sunita Shelar (25%), Parth Madan (25%) | |
Date Prepared | June 11, 2019 |
Accomplishments Of The Week | ||
---|---|---|
| ||
Team Availability | ||
Sita on leave - 2 days, Rupam on leave - 1 day, eGov Holiday - 1 day | ||
eSankalan
| ||
Marketing
|
Plans For Next Week | ||
---|---|---|
|